Marsamxett Zone Regeneration
Home/ Projects
Valletta

Marsamxett Zone Regeneration

About this project

Lower Valletta

The Lower part of Valletta basically extends from the Due Balli area near Fort St. Elmo up to St. Mark Street on the Marsamxett Harbour side of the city. It is an area situated behind a line of fortification constructed in the 1570s by the Order of St John on the design of military engineer Francesco Lapparrelli, as part of the defensive lines that encase the city.

In 2018, the Grand Harbour Regeneration Corporation was entrusted with a €25 million European-funded regeneration project. This holistic project had to include various objectives from the cultural, social and economical aspects of this particular area.

Locality Valletta
Status Finished
Launched 2025
Project phases
Bastions & fortifications 2 phases · 2018
Churches, domes & historic buildings 5 phases · 2017–2018
Mattia Preti Square housing blocks 6 phases · 2020–2022
Housing, façades & properties 8 phases · 2018–2022
Streets, pavements & public spaces 5 phases · 2021–2022
Lifts, shrines & digital 3 phases · 2018

Works by area

Every intervention, from how it was to how it is today. Select a photo to view it in full.

2 phases · 2018

Bastions & fortifications

The German, St Sebastian, English and French Curtains form the Marsamxett side of Valletta's fortifications. Some 12.5km² of walls, including Jews' Sally Port, were restored alongside new pavements, walkways and replanting.

2018 Restoration of the French & English Curtain Bastions
2018 Restoration of the German & St Sebastian Bastions
5 phases · 2017–2018

Churches, domes & historic buildings

Façades and domes of Tal-Pilar Church, the Auberge de Bavière, the House of Catalunya, Auberge d'Aragon, the Carmelite priory and the Carmelite Basilica dome.

2017 Restoration of the Façade of Tal-Pilar Church
2017 Restoration of the St Augustine Church Dome
2018 Restoration of the Auberge de Bavière Façades
2018 Restoration of the Façades of Auberge d'Aragon & the House of Catalunya
2018 Restoration of the Mount Carmel Basilica Dome
6 phases · 2020–2022

Mattia Preti Square housing blocks

Some 160 apartments around Mattia Preti Square receiving upgraded façades and common parts, energy-saving windows and balconies, lifts and services.

2020 Upgrading of Block 4, Mattia Preti Square
2021 Upgrading of Block 3, Mattia Preti Square
2021 Installation of Travertine on the Block 4 Façades
2022 Upgrading of Block 1, Mattia Preti Square
2022 Upgrading of Block 2, Mattia Preti Square
2022 Upgrading of the Pavements around Blocks 1, 2 & 3
8 phases · 2018–2022

Housing, façades & properties

Bridges on Fountain Street, the Fuq il-Blata façades and a better-living scheme rehabilitating residences across the area, many with new lifts.

2018 Upgrading of the Property at 90, West Street
2018 Upgrading of Properties 3–6, Carmelite Street
2018 Upgrading of the Property at 20, St Charles Street
2018 Upgrading of the Property at 34, Old Mint Street
1 / 2
2018 Upgrading of the Pavement at Fuq il-Blata
2020 Restoration of the Blata Façades
2020 Installation of New Bridges at Fountain Street
2022 Upgrading of Blocks A, B, C & D, Fountain Street
5 phases · 2021–2022

Streets, pavements & public spaces

Around 1,600m² pedestrianised with upgraded underground services, new paving and street embellishments, from Boat Street to Independence Square.

2021 Upgrading of Carmelite, Bounty & St Anne Streets
2021 Upgrading of the Pavements at Marsamxett Road & St Sebastian Street
2022 Pavements at Boat Street
2022 Upgrading of Independence Square
2022 Peacock Garden
3 phases · 2018

Lifts, shrines & digital

Passenger lifts for residents, the conservation of street shrines and statues, and a mobile application bringing Marsamxett's history to life.

2018 Passenger Lifts, Blocks A, B & 69E
1 / 2
2018 Development of a Mobile Application
1 / 2

Project updates

27 MAY
2024
08 APR
2024
27 FEB
2024
19 DEC
2021
30 MAR
2021
09 JUN
2020
27 FEB
2020